San Remo Towers, a Grade II listed residential development in a conservation area near Bournemouth, required a complete refurbishment of its 600m² roof terrace.

Download Project PDF

Key Statistics

Specialist Roofing Contractor Roofsmiths LLP
Project size 600m2
Substrate Concrete
WestWood products SA-VCL fixed with bonding agent 90 mm PIR Insulation bonded with adhesive Cement Board bonded with adhesive Wecryl 176 WMP 113 Wecryl 815 Wecryl 810 Wecryl 842 Wecryl R230 thix Wecryl R230 Wecryl 333 Finish Wecryl 488 grout layer Wecryl 420 tile effect + Deco Chips

The Challenge

The terrace had issues with standing water and, being in a coastal location, was exposed to harsh marine conditions and weathering. The challenge was to create a solution that not only provided robust waterproofing but also offered an aesthetically pleasing finish to suit the unique style of the development. The intricate design needed to maintain precision, particularly with the tile effect application across raised deck areas, which required exceptional attention to detail

The Solution

Roofsmiths LLP, specialists in high-quality installations, specified WestWood’s PMMA liquid waterproofing solution for its durability and UV stability, ideal for the marine environment of San Remo Towers.

The tile effect finish was created using 6mm tape, applied by hand, to form precise grout lines over the terrace, including the challenging raised areas. This process was managed by a skilled operative, ensuring the diagonal design remained straight even as it continued over the 180-meter perimeter.

Highest Quality Standards

The WestWood system not only resolved the standing water issues but also enhanced the thermal performance of the building, providing a robust, trafficable surface for residents. Weekly site visits by WestWood’s regional field technicians offered continuous support and ensured the project maintained the highest quality standards throughout.

Marine-grade waterproofing performance

WestWood’s PMMA liquid waterproofing system was selected for its durability and UV stability, making it well suited to the coastal environment at San Remo Towers.

Precision tile effect finish

The terrace finish was created using 6mm tape applied by hand to form precise grout lines, including across raised deck areas and around the 180-metre perimeter.

Improved drainage and thermal insulation

The completed roof terrace now delivers effective drainage with no standing water while also improving the building’s thermal insulation.

Trafficable surface with long-term guarantee

The system created a robust, trafficable finish for residents and delivered exceptional waterproofing backed by a 20-year guarantee.

The Outcome

The roof terrace at San Remo Towers now offers effective drainage with no standing water, improved thermal insulation, and exceptional waterproofing with a 20-year guarantee. The intricate tile effect design was completed with precision, transforming the terrace into a functional and visually appealing space for residents. The project won ‘Project of the Year’ at the National Federation of Roofing Contractors (NFRC) in 2021, showcasing the successful collaboration between Roofsmiths LLP and WestWood in delivering a high-quality, long-lasting solution